Overview
- January 2013: Environmental Assessment Certificate issued
- May - August 2013: Provincial and federal permits issued
- August - December 2013: Clearing project area and conduct investigative works
- Spring 2014 - Spring 2017: Civil construction
- 2016: Completion of the ULHP transmission line
- 2017: Completion of Boulder Creek and Upper Lillooet River hydroelectric facilities
- 2017 - 2019: Commissioning